Amelia Scott Project on Target

Plans are in place for the completion of the project

At the full council meeting of Tunbridge Wells Borough on Wednesday (7 July), the question was raised on the delay of completion of the Amelia building.

Councilor March, portfolio holder for Culture and Leisure, reported that the base build is due to be completed on 5 August 2021.

From 16 August, the fit-out contract is due to start, with a completion date at the end of the year.

There will then be a three-month period while the library is re-located and the various gallery areas fitted with their initial displays. The intention is for the Amelia to open in April 2022.

 

More from WEST KENT NEWS

On Air Now Mid Morning Golden Greats 10:00am - Noon
Now Playing
Under Pressure Queen And David Bowie
Recently Played
  • Events Guide West Kent Radio 11:12
  • Rhythm Of My Heart Rod Stewart 11:08
  • [Take A Little] Piece Of My Heart Erma Franklin 11:05

COMING UP

  • Rob Carter

    Noon - 2:00pm

    Lunch Break sponsored by Arty Farty Retreat

  • Afternoons

    2:00pm - 4:00pm

    West Kent's All Music Afternoons